Work Completed to Date at the 522 Site
· Silt Sock Installation
· Topsoil Stripping
· Earthwork around the building appeared substantially complete
· Earthwork at the future building pad appeared substantially complete
· Earthwork at the waste area (future parking) appeared 20% complete
· Nearly half of the basement excavation